East Devon Clear up to take at least six weeks

Huw Oxburgh
Authored by Huw Oxburgh
Posted Tuesday, February 11, 2014 - 4:26pm

Repair and clear-up work after damage from the latest storms is expected to take at least six weeks according to East Devon District Council.

Collapsing beach huts, damaged seafronts and a washed away ice cream parlour have all been handled by Council staff in the recent work to clear the damage left by weeks of severe weather conditions.

However, with more strong gales and heavy rain expected to hit the county late tonight and throughout the day tomorrow bringing the risk of further damage, the clear-up work may take even longer than expected.

The Met Office’s Chief forecaster said: “Another Atlantic depression is expected to bring a spell of heavy rainfall and very strong winds to parts of the UK on Wednesday. 

“Falling soon after earlier widespread rainfall, the cumulative effects of these weather systems are likely to exacerbate the current flooding situation.

“Current ideas suggest that parts of western England, Wales and northern England will bear the brunt with gusts of 60-70 mph widely, perhaps with gusts of 80-90 mph in exposed parts of north and west Wales and northwest England.”

Once the debris has been cleared and the storms subside, attention will turn to repairs, including making good damaged beach huts at Jacob’s Ladder Beach, Sidmouth. Repair work is expected to cost several thousand pounds and take at least six weeks.


To the west of the district (Exmouth and Budleigh areas), up to 18 members of staff spent the early days of the latest storms filling and deploying sandbags around the sea front area and interlinking area, which prevented some of the properties there from flooding.

Around 360 bags were used and some were dropped outside the depot gates for members of the public to help themselves. Areas affected by the high night time tides already had a supply of sandbags. EDDC staff also he handed out empty sandbags to members of the public who called at the Camperdown Depot for them, to fill as they wished.

Staff in the West team also assisted in the removal of the contents of an Ice cream business which had collapsed onto the beach, (freezers, and other sundries, parts of the hoarding and structure of the building.) The wooden building was at one point lashed to two four-wheel drive vehicles on the esplanade to stop it floating away on the tide. It later had to be dismantled.

As and when necessary, the 18 council staff were involved in cleaning up after flood water and clearing debris and masonry from the roads and drains. Further clean ups are scheduled this week, with a large 35 cubic-metre skip being placed in Lime Kiln Car Park at Budleigh for the disposal of several tonnes of sea debris and landslip material deposited on the beach and esplanade.


Work included recovering damaged and lost life saving appliances, including rings, ropes, posts and signs. Exmouth’s sea front wall sustained structural damage in five places and contractors were brought in to make emergency temporary repairs. One seafront shelter has lost several windows including part of the side frame and some brickwork was demolished.

The metal railings at the bottom of the closed Mamhead Slipway in Exmouth have been completely twisted and distorted.

Later in the week, staff turned their attention to righting overturned beach huts in Budleigh, and clearing small landslides/cliff falls on the sea front area, followed later by the clearance of debris.

Significant quantities of sand have been lost through wind or water from Exmouth’s dunes. Any sand found on the road or the footway will be returned to the beach but any sand lost in the waves cannot be replaced – unless nature takes a hand at some future date.

There have been six back office staff/ managers involved in managing the incoming workload and necessary inspections during and after the storms. EDDC staff have also been felling, cutting up and removing fallen or leaning trees.

In some cases, work has been done only for staff to have to return to clear up another mess left by the next storm.

In the East of the district (Sidmouth and Seaton coastline) the story was much the same.

Two staff responded to a call at 21.30 on Tuesday evening (4 February) to deliver sand bags in the town to the Mocha restaurant, which was already being flooded. Unfortunately the Mocha, Dukes and the Bedford were still affected by flooding.

Crews were deployed to cut up and remove any dangerous trees in the Sidmouth area. A further 10 trees were blown over but most were safe on the ground and work was delayed until after the initial clear up.

A contractor was called in at Seaton to remove shingle that had built up against the sea wall to allow the wave return to do its job and protect properties there from possible flooding at the next high tide. Five staff worked hard delivering and helping residents build deflection barriers to divert the sea away from their properties in Seaton. Around 150 sandbags were delivered.

Later in the week, a dozen staff worked on clearing up the seafront roads so they could be reopened. A contractor was again brought in with a JCB to remove the broken walls and shingle from the road at Seaton.

The main driving area on Sidmouth seafront was cleared by EDDC’s own mechanical sweeper. The turning circle at the Port Royal end was so deep in pebbles and broken tarmac that a contractor was called in on Monday (10 February) to clear it.

Many benches and bins have been destroyed. EDDC will be removing memorial plaques from benches and contacting the owners.

Eight office staff and managers have been directing the clear up and dealing with calls from the storms.

Once the debris has been cleared and the storms subside, attention will turn to repairs, including making good damaged beach huts at Jacob’s Ladder Beach, Sidmouth. Repair work is expected to cost several thousand pounds and take at least six weeks.

Share this