Major scheme to prevent sewer flooding in Exmouth
A £736,000 scheme to prevent sewer flooding in Exmouth gets under way next month.
South West Water will be constructing new surface water sewers to remove surface water from the sewerage network and making other improvements to prevent internal and external sewer flooding in the town and reduce the risk of pollution to the Exe Estuary.
Work starts on Monday 5 January and will be completed by Friday 3 April 2015.
The work is centred at two locations:
Camperdown Terrace: Construction of new surface water sewers, undertaking surface water separation at 20 houses, construction of three new surface water outfalls and two small pumping stations.
The Strand: Reconfiguration of the local sewerage system and construction of a small pumping station.
Project manager Andy Young said: "Sewer flooding is unpleasant enough when it affects roads and open spaces but can be devastating when it affects homes and businesses.
"Camperdown Terrace and The Strand are currently served by a combined sewerage system - pipes that take both waste water from homes and businesses and surface water from roads and roofs. During times of heavy rainfall, they can struggle to cope with the volume of incoming surface water, which can lead to flooding.
"This project will go a long way to alleviate flooding and pollution in the area."
A number of roads will need to be temporarily closed to traffic during construction:
Camperdown Terrace - Monday 5 January to Saturday 14 February 2015
Trinity Road - Monday 16 February to Friday 6 March 2015
Queen Street/rear of The Strand - Monday 23 February to Friday 27 March 2015
Point Terrace - Monday 9 March to Friday 27 March 2015
During the Camperdown Terrace closure, the bollards between Camperdown Terrace and Shelly Road will be temporarily removed to allow residents to access their properties.
A dedicated customer liaison officer has been appointed for the scheme to ensure local residents are kept up to date.